A bathroom plays out over a few square metres, but it calls for many decisions: where each fitting goes, what gets tiled and what gets painted, the tile layout, the light, the sockets. Here are the ideas, techniques and points of attention that make for a calm building site, a foretaste of working with an architect.
Reversing the swing of a door can free up space without major work on the wall.
In our project in Bertem, a 2.40m by 2.10m bathroom, redone in the same place as before. Everything came down to circulation, layout and light.
Tiling only where water splashes keeps the investment down: the shower, a splashback at the basin. The rest is painted.
Tiles mainly do two things: resist water where it splashes, and clean easily. On their own they do not make the wall watertight: waterproofing goes under the tiles, as a membrane or a coating suited to the substrate. A gypsum-based substrate always gets a membrane where water splashes directly.
Elsewhere, nothing requires tiles. You can place tiles in the strategic spots and switch to other finishes: a paint made for damp rooms, a lime or clay plaster, polished concrete or microcement. Each has its own application and maintenance conditions, to be checked in the manufacturer’s data sheet. Gypsum, air lime and clay plasters do not like moisture: Buildwise advises against them on walls often exposed to splashing, such as a shower, unless they are waterproofed. A heated and ventilated private bathroom is not, however, considered a wet room. Polished concrete does not, on its own, make a shower watertight.
What each option costs per square metre is in the price benchmarks further down.
The same wall, and sometimes the floors, can be finished differently. Polished concrete or microcement, often known by a brand name such as mortex, goes on in thin coats on walls and floors alike. Tadelakt, a lime plaster polished with a stone and fed with black soap, is used in hammams. Clay and lime breathe and regulate the room’s humidity. None is watertight on its own in a shower: each needs its complete system, or a membrane underneath, according to the manufacturer’s data sheet. Clay and air lime stay out of the splash zones.
Not every layout takes the same work: a diagonal or a herringbone means more cuts and more time, and that shows in the price.
The tile layout is the drawing of the tiles: their size, their colours, their direction, their offset, where you start and where the cuts fall. With the same tile, the room can look taller, wider, calmer or livelier. It is drawn wall by wall, before ordering.
Small tiles are in fashion, but they multiply the joints: more surface to maintain, more cuts and more laying. A large format, 60×60 or 60×120 rectified, reduces the joints and cleans faster. That was the choice in Sterrebeek and Bertem. Small formats still make sense as a touch: a niche, a splashback, a shower floor.
The threshold
Between two rooms on the same floor level, you can change the layout and mark the passage differently, with or without finishing profiles. Here, a walnut parquet effect on one side, a band of white squares at the threshold, then light brown squares with dark joints.
A dark joint reveals the pattern, a joint in the same tone erases it. A light joint, unless it is epoxy, can dull over time.
On a simple base of 20 × 20 squares, the joint colour changes everything: light or in the same tone, it erases the pattern, dark or coloured, it reveals it.
A shelf aligned with a tile or a joint: drawn beforehand, it falls into place.
This is often where a bathroom is won: the glass panel held in a profile, a soap dish the size of a tile, a switch centred on the grid, a built-in bench in the shower, a coloured shelf fixed in the joints. These details are drawn before the works, otherwise they do not happen.
A wall-hung cabinet frees the floor: cleaning is simpler.
Countertop, built into the top, wall-hung, on a slim frame, or under a built-in tiled ledge: the basin decides the height of the top, the storage below and the cleaning. With a countertop basin, the tap comes out of the wall or the cabinet. A wall-hung cabinet or basin frees the floor, which makes maintenance easier. Mind the load-bearing capacity of your wall. Not every wall can carry a basin with only the fixings supplied, sometimes a support such as legs is still needed.
The spotlight between the mirror and the face, not above the head.
A spotlight placed right above the head casts shadows on the face. Placed between the mirror and the face, or on each side of the mirror, it lights the face from the front. At the mirror, a neutral white of 4000 to 4500K renders colours accurately. For the bath, a warm white of 2700 to 3000K, for atmosphere.
Our rule: where they are needed, within reach, but out of sight.
First the style, chosen with the taps and light fittings. Then the position: you reach for the switch as you walk in, the socket where you do your hair and shave. They are decided before the tiling, moving them afterwards means opening the wall.
The radiator can become an object: column, a ladder for drying towels, a flat panel, a bent tube, or tucked into a niche. Its height, width and colour are yours to choose, often from the full RAL range or metal finishes, to match the colour of the joints, a wall or the tap finishes.
A shower tray set on the finished floor means stepping over a step. A level-access shower is built flush with the floor: you walk in without a step, and a wall-mounted bench with a grab rail lets you shower seated. For a walk-in tiled shower, the space for the drain must be planned and the slope is formed in the screed. The same goes for a tray: the drain position is prepared, and where the drain sits in the tray differs from one model to another.
Each wall drawn before the quote, then followed during site visits.
A bathroom is a succession of choices: some can be anticipated, others are made on the spot. We support you when you need it, so that you choose with full knowledge rather than putting up with your choices, or their absence.
For a specific question, without a full commission.
advice on your situation, comparison of contractors’ quotes, formalities, drawing of a tile layout or an elevation
To draw the room before asking for prices.
plan and elevations, tile layout wall by wall, light, sockets, fittings, interior architecture and choice of materials
When the works go beyond the bathroom, or need a permit.
design and application, tendering to contractors, site supervision
We do not answer technical questions by phone or e-mail without having looked at the situation: every bathroom has its own particularities and constraints.
They give an order of magnitude, excl. VAT: the condition of the installation and the range chosen make them vary.
A 2m by 3m bathroom renovation: level-access shower with glass panel, wall-hung basin, wall-hung WC, towel rail, floor and walls tiled in the shower and painted elsewhere.
| Demolition and removal | 1000€ |
| Plumbing, connecting the fittings | from 1000€ |
| Screed and waterproofing | 500–1500€ |
| Floor and shower tiling (varies with tile price) | 50–130€/m² |
| Painting walls and ceiling | 30–50€/m² |
| Shower (not concealed) | from 1 000€ |
| Basin and wall-hung WC | from 1500€ |
| Towel rail | from 450€ |
| Ventilation with sensors | from 750€ |
| Electrics, lighting | from 400€ |
| Total excl. VAT | 8500-10,000€ |
Demolition, screed and waterproofing
| Removing wall tiles | approx. 30€/m² |
| Removing the screed and floor tiles | 40–50€/m² |
| Cement screed, 6 to 8cm | 30–40€/m² |
| Waterproofing under tiles, floor | 30–40€/m² |
| Waterproofing under tiles, wall | 30–40€/m² |
Finishes
| Floor tiles 60×60 | 50–60€/m² |
| Wall tiles 10×10 to 30×30 | 100–130€/m² |
| Paint, primer and 2 coats | 30–50€/m² |
| Lime plaster | 50–60€/m² |
| Clay plaster | 70–80€/m² |
Shower and bath
| Walk-in tiled shower, drain included | 980–1 170€/unit |
| Shower tray | 570–1000€/unit |
| Glass shower panel | 870–1 500€/unit |
| Thermostatic mixer and hand shower | 300–400€/unit |
| Thermostatic mixer and overhead shower | 850–1 000€/unit |
| Concealed taps | 870–1 500€/unit |
| Acrylic bath | 700–1000€/unit |
Basin, WC and fittings
| Wall-hung basin | 440–1000€/unit |
| Wall-hung WC | 850–1100€/unit |
| Floor-standing WC | 550–700€/unit |
| Towel rail | from 450€/unit |
| Extractor fan with humidistat | from 750€/unit |
| Recessed LED spotlight IP65 | approx. 70€/unit |
The membrane kit around the shower tray is often forgotten: plan for it.
Waterproofing goes under the tiles, on the floor and on exposed walls, with a tape in every corner, as a semi-rigid or liquid membrane. Before tiling, the plumber checks his pipes for leaks. Note that the perimeter membrane is often forgotten when fitting a shower tray or a bath, so it is best to order the kit in advance.
For water to run off, the slope of the tiled floor exceeds 10mm per metre. In a shower, the tiles must also limit the risk of slipping barefoot. The traps recommended in the technical documentation keep a water depth of at least 50mm: that is what stops odours coming back up.
Never block the gap under the door.
A bathroom is ventilated with an extraction of at least 50m³/h to the outside. Air comes in from the neighbouring rooms through a transfer opening, for example a gap of at least 70cm² under the door. This is the EPB requirement for new homes and a starting benchmark in renovation.
Our advice: ventilation that runs continuously all day, with at least a humidity sensor (performance can drop over time). If possible, choose a model with, or add, a VOC and CO₂ or presence sensor.
The electrical regulations divide the room into zones around the water. All circuits go through a residual current device of 30mA maximum. A light fitting is also chosen on the basis of its IP rating:
Hearing water running through the pipes from the bedrooms is not necessarily pleasant. The Belgian acoustic standard for housing sets maximum levels for noise from sanitary installations. To get close to it, an engineering firm can study the routing of the waste pipes, their fixing and their casing.
A healthy, heated and well-ventilated bathroom dries out. On a cold or uninsulated wall, vapour condenses and mould follows. Insulating that wall from the inside can help, but it calls for a study (thermal bridges, condition of the structure, water permeability, rising damp, etc).
The rules of good practice to remember, one diagram each.
A bathroom remains sensitive: regular maintenance protects it:
A few products
Wall-hung WC frames.
Waterproofing and uncoupling membranes under tiles.
Finishing profiles and joints in matching shades.
Porcelain tiles and mosaics for floors and walls.
Bathroom accessories and light fittings.
Want to take your bathroom project further, or another room?